Administering a contract means making sure that what was agreed gets done, at the agreed price, and that everything is documented. The golden rule, for both parties: what is not in writing does not exist.
1. Start-up
- Kick-off meeting: introduction of each party's managers, communication channels, schedule and procedures.
- Start-up documentation: signed contract, guarantees, insurance policies, ART (workers' compensation) and personnel roster, registration in the operator's vendor registry, vehicle and equipment approval.
- Safety inductions and site entry permits.
- Start-up record with the date from which the term runs.
2. During execution
- Daily reports signed by both parties: personnel, equipment, hours worked, progress, standby and interferences.
- Service order book (from the client to the contractor) and request note book (from the contractor to the client), numbered.
- Periodic progress meetings with written minutes.
- Tracking of indicators (KPIs): progress against plan, incidents, quality compliance.
3. Certification and invoicing
Each month (or each milestone) the work performed is measured and the certificate is issued: quantities per item × unit price, plus the price adjustment, minus advance payment and retainage. With the certificate approved by the client, the contractor invoices.
- Joint measurement, with criteria defined in the tender documents.
- Separate adjustment certificate, with the indices used.
- Approval deadlines: how many days the client has to approve or object.
4. Change orders and extras
- No work outside the scope is performed without a written change order approved by someone with the authority to do so.
- The change order must state what is being done, what it costs (or which contract prices it is paid at) and how it affects the schedule.
- Unforeseen events (interferences, different ground conditions, client delays) are notified at the time by request note, even if the financial claim is filed later.
5. Claims, penalties and performance
- Claims have deadlines: the contract usually sets how many days there are to file them after the event. Once that period has passed, they are lost.
- Penalties are applied as agreed and are capped; they must be notified and justified.
- The supplier's performance evaluation at the end of each contract feeds the operator's registry for future tenders.
6. Closeout
- Provisional acceptance (with a punch list) and final acceptance after the warranty period.
- Final certificate and reconciliation of quantities, adjustments and extras.
- Delivery of final documentation: quality dossier, as-built drawings, manuals.
- Return of retainage and guarantees.
- Closeout record with no pending claims (or with the pending items listed).
General guide based on common industry practice; it does not replace legal, tax or accounting advice for each case.